Delay contribution is the average number of days an activity is adding to the outturn end date, when it is critical.
Activities with high delay contribution are forecast to delay the end of the project when they become critical. High delay contribution can happen when total float is consumed by predecessors which are forecast to be late, or when other parts of the programme are forecast to be early and the activity becomes critical.